Indian Army completes Bailey Bridge over Sukhtawa River in record 6 days in Madhya Pradesh’s Narmadapuram - WATCH

Thursday, 1 September 2022 (11:59 IST)
Pune: Indian Army Engineers have completed construction of a Bailey Bridge over Sukhtawa River in Narmadapuram district of Madhya Pradesh in record time of six days.

A defence press release on Thursday here stated that the bridge was handed over to civil administration by the GOC, PMP Sub Area after the engineers of Sudarshan Chakra Corps of Southern Command Pune completed it.

The work on the bridge started on Aug 26.

The Bailey Bridge will ensure day and night connectivity and restoration of vital economic activity over Nagpur – Bhopal corridor on NH 46 in Madhya Pradesh.

The Bailey Bridge is 3.5m wide and 90 feet long single lane which is capable of sustaining heavy traffic.

This is first time in Madhya Pradesh Indian Army has made a bridge of this specification.

Indian Army Engineers of Sudarshan Chakra Corps completed the construction of bailey bridge over Sukhtawa river in Narmadapuram district in a record time of six days: Southern Command

The bridge collapsed in April 2022 due to heavy vehicular traffic (31.08) pic.twitter.com/WFQ84JjPcD

— Subodh Srivastava ???????? (@SuboSrivastava) September 1, 2022


The NHAI and civil administration provided all kind of support during the planning and construction, the release added. (UNI)